Dept. of Trans. PROGRESS Serial No. Contract No. 24-330-09-12 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 57% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 019 Payment period ending: 11-20-24 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 120,171,882.04 4,292,781.26 2. a. Extra Work 1,901,701.96 92,771.61 b. Adustment Comp. -853,763.16 -415,615.20 3. Materials on Hand 67,014.55 67,014.55 4. Earned Subject to Retention 121,286,835.39 4,036,952.22 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 134,366,667.10 7. Deductions -58,376.22 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 134,375,305.43 4,031,952.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,031,952.22