Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-08-48 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 80% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 022 Payment period ending: 02-20-25 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 121,646,321.00 656,664.76 2. a. Extra Work 3,191,953.57 238,926.02 b. Adustment Comp. -555,831.32 70,019.74 3. Materials on Hand 67,014.55 0.00 4. Earned Subject to Retention 124,349,457.80 965,610.52 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 137,429,289.51 7. Deductions -68,376.22 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 137,427,927.84 965,610.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 965,610.52