Dept. of Trans. PROGRESS Serial No. Contract No. 25-083-12-05 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 84% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 023 Payment period ending: 03-20-25 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 122,236,099.10 589,778.10 2. a. Extra Work 3,425,655.15 233,701.58 b. Adustment Comp. -494,172.67 61,658.65 3. Materials on Hand 67,014.55 0.00 4. Earned Subject to Retention 125,234,596.13 885,138.33 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 138,314,427.84 7. Deductions -58,376.22 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 138,323,066.17 895,138.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 895,138.33