Dept. of Trans. PROGRESS Serial No. Contract No. 25-141-14-51 02-3H32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 83% Location: Federal Project: 02-SIS-5-2.5/R15.9 ACNH-059(181) Progress payment No. 025 Payment period ending: 05-20-25 WALSH-MYERS JOINT VENTURE 929 W ADAMS ST CHICAGO IL 60607 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 125,977,888.37 1,108,532.85 2. a. Extra Work 3,690,615.08 135,489.41 b. Adustment Comp. 618,955.30 1,093,286.17 3. Materials on Hand 0.00 -67,014.55 4. Earned Subject to Retention 130,287,458.75 2,270,293.88 5. Mobilization 13,146,846.26 0.00 6. Total Work Completed 143,434,305.01 7. Deductions -58,376.22 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 143,375,928.79 2,270,293.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,270,293.88