Dept. of Trans. PROGRESS Serial No. Contract No. 17-160-08-06 02-3H3804 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 65% Location: Federal Project: 02-TRI-299-39.2/39.2 NONE Progress payment No. 001 Payment period ending: 06-06-17 J.F. SHEA CONSTRUCTION INC. PO BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 421,443.74 421,443.74 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 421,443.74 421,443.74 5. Mobilization 6. Total Work Completed 421,443.74 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 421,443.74 421,443.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 421,443.74