Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-305-13-39 02-3H4204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-SHA-910 HSNH-X089(122) Progress payment No. 004 Payment period ending: 08-24-18 GOLDEN BAY FENCE PLUS IRON WORKS INC 4104 S B ST STOCKTON CA 95206 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 469,582.06 10,518.17 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 469,582.06 10,518.17 5. Mobilization 6. Total Work Completed 469,582.06 7. Deductions 0.00 23,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 469,582.06 33,518.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,518.17