Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 26-208-08-43 02-3H70U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-TRI-299-15.0/25.7 ACNH-P299(217) Progress payment No. 015 Payment period ending: 06-05-26 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,512,695.04 226,486.06 2. a. Extra Work 238,764.85 4,891.56 b. Adustment Comp. 6,754.78 61,110.35 3. Materials on Hand 4. Earned Subject to Retention 14,758,214.67 292,487.97 5. Mobilization 2,345,000.00 0.00 6. Total Work Completed 17,103,214.67 7. Deductions -41,000.00 582,386.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,062,214.67 874,873.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 874,873.97