Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 26-278-09-21 02-3H7704 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 61% Location: Federal Project: 02-TEH-99-0.0/12.5 ACNH-P099(695) Progress payment No. 008 Payment period ending: 10-02-26 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,888,366.06 183,416.85 2. a. Extra Work 716,482.15 312,148.95 b. Adustment Comp. -7,476.90 0.00 3. Materials on Hand 15,080.53 15,080.53 4. Earned Subject to Retention 22,612,451.84 510,646.33 5. Mobilization 3,640,000.00 0.00 6. Total Work Completed 26,237,371.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,252,451.84 510,646.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 510,646.33