Dept. of Trans. PROGRESS Serial No. Contract No. 20-245-12-41 02-3H8104 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 19% Location: Federal Project: 02-PLU-70 NONE Progress payment No. 003 Payment period ending: 08-20-20 Q & D CONSTRUCTION INC PO BOX 10865 RENO NV 89510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 684,712.13 14,000.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 684,712.13 14,000.00 5. Mobilization 219,026.11 0.00 6. Total Work Completed 903,738.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 903,738.24 14,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,000.00