Dept. of Trans. PROGRESS Serial No. Contract No. 24-170-15-46 02-3H82U4 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 25% Location: Federal Project: 02-LAS-44-0.0/37.2 HSNH-P044(60) Progress payment No. 002 Payment period ending: 06-20-24 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,649,799.40 1,905,230.05 2. a. Extra Work 2,798.04 -6,000.00 b. Adustment Comp. 3. Materials on Hand 0.00 -167,590.66 4. Earned Subject to Retention 2,652,597.44 1,731,639.39 5. Mobilization 1,697,625.38 1,697,625.38 6. Total Work Completed 4,350,222.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,350,222.82 3,429,264.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,429,264.77