Dept. of Trans. PROGRESS Serial No. Contract No. 24-299-08-55 02-3J3204 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 15% Location: Federal Project: 02-VAR NONE Progress payment No. 001 Payment period ending: 10-20-24 Q&D CONSTRUCTION LLC PO BOX 10865 RENO NV 89510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 388,778.35 388,778.35 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 388,778.35 388,778.35 5. Mobilization 245,000.00 245,000.00 6. Total Work Completed 633,778.35 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 628,778.35 628,778.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 628,778.35