Dept. of Trans. PROGRESS Serial No. Contract No. 24-151-11-52 02-3J4904 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 17% Location: Federal Project: 02-SIS-3-R46.8/R48.0 NONE Progress payment No. 002 Payment period ending: 05-20-24 MYERS SHEA A JOINT VENTURE 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 118,489.14 118,489.14 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 204,471.79 -22,719.09 4. Earned Subject to Retention 322,960.93 95,770.05 5. Mobilization 192,203.45 40,463.88 6. Total Work Completed 310,692.59 7. Deductions -100,461.77 51,277.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 414,702.61 187,511.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 187,511.73