Dept. of Trans. PROGRESS Serial No. Contract No. 24-171-13-09 02-3J4904 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 35% Location: Federal Project: 02-SIS-3-R46.8/R48.0 NONE Progress payment No. 003 Payment period ending: 06-20-24 MYERS SHEA A JOINT VENTURE 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 751,017.62 632,528.48 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 124,954.98 -79,516.81 4. Earned Subject to Retention 875,972.60 553,011.67 5. Mobilization 202,319.42 10,115.97 6. Total Work Completed 953,337.04 7. Deductions -39,955.65 60,506.12 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,038,336.37 623,633.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 623,633.76