Dept. of Trans. PROGRESS Serial No. Contract No. 23-166-09-39 02-3J8004 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 33% Location: Federal Project: 02-TRI-3-11.0/R26.3 NONE 02-TRI-3-38.0/42.0 Progress payment No. 001 Payment period ending: 06-20-23 VSS INTERNATIONAL INC 3785 CHANNEL DRIVE WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 920,602.60 920,602.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 920,602.60 920,602.60 5. Mobilization 6. Total Work Completed 920,602.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 920,602.60 920,602.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 920,602.60