Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-057-12-30 02-3J9904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-SIS-3-R46.8/R48.0 NONE Progress payment No. 005 Payment period ending: 02-02-24 MYERS SHEA A JOINT VENTURE 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 495,326.40 9,906.53 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 495,326.40 9,906.53 5. Mobilization 86,873.38 0.00 6. Total Work Completed 582,199.78 7. Deductions -10,000.00 18,653.41 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 572,199.78 28,559.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,559.94