Dept. of Trans. PROGRESS Serial No. Contract No. 19-295-10-16 02-4C1504 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 22% Location: Federal Project: 02-SIS-96-23.4/54.5 B1ST-P096(61) Progress payment No. 002 Payment period ending: 10-20-19 HAYES & SONS INC PO BOX 258 HAPPY CAMP CA 96039 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 907,051.00 728,561.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -125,967.35 4. Earned Subject to Retention 907,051.00 602,593.85 5. Mobilization 266,000.00 56,000.00 6. Total Work Completed 1,173,051.00 7. Deductions -47,993.72 -14,051.31 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,125,057.28 644,542.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 644,542.54