Dept. of Trans. FINAL Serial No. Contract No. 07-047-09-38 02-4C2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SIS-97-24.0/52.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-20-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,261,146.06 0.00 2.a. Extra Work 12,697.24 0.00 b. Adjustment Comp. -70,156.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,203,686.60 0.00 5. Mobilization 6. Total Work Completed 1,203,686.60 7. Deductions 8. a.Contract Retentions -58,711.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 58,711.90 0.00 9. Total pay to Contractor 1,203,686.60 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00