Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-09-30 02-4C2904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 88% 02-LAS-36-6.7/10.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-10 OUTBACK DVBE INC P O BOX 1035 RED BLUFF CA 96080 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 620,179.41 21,550.26 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 620,179.41 21,550.26 5. Mobilization 6. Total Work Completed 620,179.41 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 620,179.41 21,550.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,550.26