Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 19-339-15-01 02-4C40V4 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 31% Location: Federal Project: 02-SHA-5-R3.8/R11.7 B1IM-005-8(359) Progress payment No. 011 Payment period ending: 11-20-19 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,854,069.61 535,200.00 2. a. Extra Work 1,711,550.36 559,646.34 b. Adustment Comp. 59,971.55 0.00 3. Materials on Hand 1,907,445.00 0.00 4. Earned Subject to Retention 43,533,036.52 1,094,846.34 5. Mobilization 11,760,074.70 0.00 6. Total Work Completed 53,385,666.22 7. Deductions -309,550.78 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 54,983,560.44 1,094,846.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,094,846.34