Dept. of Trans. PROGRESS Serial No. Contract No. 21-204-16-00 02-4C40V4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 86% Location: Federal Project: 02-SHA-5-R3.8/R11.7 B1IM-005-8(359) Progress payment No. 032 Payment period ending: 07-20-21 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 95,233,098.14 2,779,356.69 2. a. Extra Work 7,938,265.46 1,329,425.38 b. Adustment Comp. -1,140,284.03 0.00 3. Materials on Hand 47,231.56 0.00 4. Earned Subject to Retention 102,078,311.13 4,108,782.07 5. Mobilization 12,379,026.00 0.00 6. Total Work Completed 114,410,105.57 7. Deductions -322,424.53 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 114,134,912.60 4,108,782.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,108,782.07