Dept. of Trans. PROGRESS Serial No. Contract No. 21-295-13-58 02-4C40V4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 96% Location: Federal Project: 02-SHA-5-R3.8/R11.7 B1IM-005-8(359) Progress payment No. 035 Payment period ending: 10-20-21 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,467,658.35 1,768,421.09 2. a. Extra Work 8,569,172.64 229,312.49 b. Adustment Comp. -1,141,628.13 0.00 3. Materials on Hand 4. Earned Subject to Retention 108,895,202.86 1,997,733.58 5. Mobilization 12,379,026.00 0.00 6. Total Work Completed 121,274,228.86 7. Deductions -327,424.53 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 120,946,804.33 1,992,733.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,992,733.58