Dept. of Trans. PROGRESS Serial No. Contract No. 08-234-14-31 02-4C5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 56% 02-VAR Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-08 DEBRUIN CONSTRUCTION INC P O BOX 1355 FRENCH CAMP CA 95231 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 258,018.84 227,326.84 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 258,018.84 227,326.84 5. Mobilization 61,750.00 61,750.00 6. Total Work Completed 319,768.84 7. Deductions 8. a.Contract Retentions -20,609.16 -17,539.96 b. Unsatisfactory Prog. -5,192.72 -5,192.72 c. Reduction after 95% Comp. 9. Total pay to Contractor 293,966.96 266,344.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,344.16