Dept. of Trans. PROGRESS Serial No. Contract No. 10-238-13-42 02-4C5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 28% 02-TEH-99-11.6/12.6 Federal Project: ARRA-P099(525) L-P099(525) Progress payment No. 02 Payment period ending: 08-20-10 RON HALE CONSTRUCTION INC P O BOX 795 SHASTA LAKE CA 96019 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,890.30 147,918.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 22,596.69 20,641.85 4. Earned Subject to Retention 179,486.99 168,560.55 5. Mobilization 11,250.00 11,250.00 6. Total Work Completed 168,140.30 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 190,736.99 179,810.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,810.55