Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-282-12-06 02-4C6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-299-67.8/77.9 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-19-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,736,974.54 313,950.43 2.a. Extra Work 154,787.26 154,787.26 b. Adjustment Comp. -171,003.97 -171,003.97 3. Materials on Hand 4. Earned Subject to Retention 2,720,757.83 297,733.72 5. Mobilization 6. Total Work Completed 2,720,757.83 7. Deductions -12,000.00 -10,000.00 8. a.Contract Retentions -121,151.21 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 121,151.21 121,151.21 9. Total pay to Contractor 2,708,757.83 408,884.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 408,884.93