Dept. of Trans. PROGRESS Serial No. Contract No. 10-203-13-31 02-4C8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 22% 02-PLU-70-38.5/ .0 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-10 DIG IT CONSTRUCTION INC P O BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 105,522.06 105,522.06 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 105,522.06 105,522.06 5. Mobilization 6. Total Work Completed 105,522.06 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 105,522.06 105,522.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,522.06