Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-194-14-00 02-4C8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-PLU-70-R43.2/45.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-23-09 ROBERT J FRANK CONSTRUCTION INC 2806 TARMAC ROAD REDDING CA 96003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 120,866.05 26,644.05 2.a. Extra Work 379.20 379.20 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 121,245.25 27,023.25 5. Mobilization 6. Total Work Completed 121,245.25 7. Deductions -12,664.40 -12,664.40 8. a.Contract Retentions -4,711.10 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 4,711.10 4,711.10 9. Total pay to Contractor 108,580.85 19,069.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,069.95