Dept. of Trans. PROGRESS Serial No. Contract No. 14-143-11-15 02-4E4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 12% 02-TRI-299-53.5/64.0 Federal Project: NHP-P299(179) Progress payment No. 01 Payment period ending: 05-21-14 J. F. SHEA CONSTRUCTION, INC. P. O. BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 254,633.38 254,633.38 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 254,633.38 254,633.38 5. Mobilization 65,000.00 65,000.00 6. Total Work Completed 319,633.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 319,633.38 319,633.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 319,633.38