Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-002-12-51 02-4E4204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-LAS-395-R0.0/R5.6 ACST-000C-4(45E) Progress payment No. 009 Payment period ending: 10-09-17 SIERRA NEVADA CONSTRUCTION INC 2055 E. GREG ST SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,229,244.35 7,395.00 2. a. Extra Work 392,790.34 1,828.65 b. Adustment Comp. 53,200.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,675,234.69 9,223.65 5. Mobilization 500,000.00 0.00 6. Total Work Completed 10,175,234.69 7. Deductions 0.00 26,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,175,234.69 35,723.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,723.65