Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-044-08-38 02-4E4504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-LAS-299-18.5/25.6 ACST-000C(519) Progress payment No. 013 Payment period ending: 06-29-23 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,583,858.67 104,823.04 2. a. Extra Work 2,427,371.58 173,164.16 b. Adustment Comp. 436,961.18 -26,000.00 3. Materials on Hand 4. Earned Subject to Retention 17,448,191.43 251,987.20 5. Mobilization 1,650,000.00 0.00 6. Total Work Completed 19,098,191.43 7. Deductions -75,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,023,191.43 261,987.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,987.20