Dept. of Trans. PROGRESS Serial No. Contract No. 13-326-10-51 02-4E5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 42% 02-VAR Federal Project: NONE Progress payment No. 04 Payment period ending: 11-19-13 TRUESDELL CORPORATION OF CALIFORNIA INC 1310 W 23RD STREET TEMPE AZ 85282 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 774,170.10 61,178.00 2.a. Extra Work 29,981.47 5,023.70 b. Adjustment Comp. -20,000.00 0.00 3. Materials on Hand 10,391.35 10,391.35 4. Earned Subject to Retention 794,542.92 76,593.05 5. Mobilization 173,025.73 0.00 6. Total Work Completed 957,177.30 7. Deductions -4,000.00 6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 963,568.65 82,593.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,593.05