Dept. of Trans. PROGRESS Serial No. Contract No. 17-233-12-21 02-4E6404 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 38% Location: Federal Project: 02-PLU-147-8.9/9.3 STP-P147(3) Progress payment No. 005 Payment period ending: 08-20-17 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,566,878.15 565,801.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 22,111.00 -15,554.38 4. Earned Subject to Retention 1,588,989.15 550,247.12 5. Mobilization 541,500.00 114,000.00 6. Total Work Completed 2,108,378.15 7. Deductions -205,030.53 -205,030.53 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,925,458.62 459,216.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 459,216.59