Dept. of Trans. PROGRESS Serial No. Contract No. 17-360-15-33 02-4E6404 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 72% Location: Federal Project: 02-PLU-147-8.9/9.3 STP-P147(3) Progress payment No. 009 Payment period ending: 12-20-17 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,843,921.55 441,239.50 2. a. Extra Work 50,440.39 34,181.81 b. Adustment Comp. 3. Materials on Hand 34,728.00 -138,911.00 4. Earned Subject to Retention 3,929,089.94 336,510.31 5. Mobilization 570,000.00 0.00 6. Total Work Completed 4,464,361.94 7. Deductions -574,754.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,924,335.94 341,510.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 341,510.31