Dept. of Trans. PROGRESS Serial No. Contract No. 18-019-15-02 02-4E6404 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 75% Location: Federal Project: 02-PLU-147-8.9/9.3 STP-P147(3) Progress payment No. 010 Payment period ending: 01-20-18 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,891,234.05 47,312.50 2. a. Extra Work 50,440.39 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -34,728.00 4. Earned Subject to Retention 3,941,674.44 12,584.50 5. Mobilization 570,000.00 0.00 6. Total Work Completed 4,511,674.44 7. Deductions 0.00 574,754.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,511,674.44 587,338.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 587,338.50