Dept. of Trans. PROGRESS Serial No. Contract No. 20-141-12-45 02-4F2004 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 88% Location: Federal Project: 02-SHA-44-59.4/59.8 B1NH-P044(57) Progress payment No. 008 Payment period ending: 05-20-20 STEELHEAD CONSTRUCTORS INC PO BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,497,938.12 -60,172.00 2. a. Extra Work 528,374.41 211,575.82 b. Adustment Comp. -47,293.50 -47,293.50 3. Materials on Hand 4. Earned Subject to Retention 4,979,019.03 104,110.32 5. Mobilization 550,000.00 0.00 6. Total Work Completed 5,529,019.03 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,523,019.03 98,110.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,110.32