Dept. of Trans. PROGRESS Serial No. Contract No. 19-086-10-04 02-4F2104 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 0% Location: Federal Project: 02-MOD-299-0.5 B1ST-P299(204) Progress payment No. 001 Payment period ending: 03-20-19 WEST COAST CONTRACTORS INC 61050 HWY 101 COOS BAY OR 97420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 136,309.11 136,309.11 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 136,309.11 136,309.11 5. Mobilization 6. Total Work Completed 136,309.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 136,309.11 136,309.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,309.11