Dept. of Trans. PROGRESS Serial No. Contract No. 20-085-10-10 02-4F2104 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 84% Location: Federal Project: 02-MOD-299-0.5 B1ST-P299(204) Progress payment No. 012 Payment period ending: 03-20-20 WEST COAST CONTRACTORS INC 61050 HWY 101 COOS BAY OR 97420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,208,044.92 0.00 2. a. Extra Work 79,275.52 5,665.10 b. Adustment Comp. -10,000.00 0.00 3. Materials on Hand 502,914.28 381,606.28 4. Earned Subject to Retention 3,780,234.72 387,271.38 5. Mobilization 690,000.00 0.00 6. Total Work Completed 3,967,320.44 7. Deductions -31,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -127,933.61 -38,727.14 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,311,301.11 318,544.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 318,544.24