Dept. of Trans. PROGRESS Serial No. Contract No. 21-327-12-23 02-4F2204 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 42% Location: Federal Project: 02-TRI-3-58.7/60.7 ACST-P003(36) Progress payment No. 006 Payment period ending: 11-20-21 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,579,662.50 406,285.68 2. a. Extra Work 304,027.37 110,574.37 b. Adustment Comp. 103,844.78 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,987,534.65 516,860.05 5. Mobilization 1,059,233.85 0.00 6. Total Work Completed 6,046,768.50 7. Deductions -6,620.00 -5,620.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,040,148.50 511,240.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 511,240.05