Dept. of Trans. FINAL Serial No. Contract No. 24-117-10-10 02-4F2204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-TRI-3-58.7/60.7 ACST-P003(36) Progress payment No. 028 Payment period ending: 10-26-23 MCCULLOUGH CONSTRUCTION INC 57 ALDER GROVE RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,570,518.72 -150,629.00 2. a. Extra Work 610,933.80 0.00 b. Adustment Comp. 516,519.86 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,697,972.38 -150,629.00 5. Mobilization 1,114,983.00 0.00 6. Total Work Completed 12,812,955.38 7. Deductions -5,620.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,807,335.38 -150,629.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -150,629.00