Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-231-10-57 02-4F4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-5-R34.3/R36.8 Federal Project: HSNH-058(351) Progress payment No. 03 Payment period ending: 08-01-14 TULLIS, INC. P.O. BOX 493416 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,514,678.78 84,448.30 2.a. Extra Work 41,010.83 1,524.90 b. Adjustment Comp. -6,474.04 -12,712.04 3. Materials on Hand 4. Earned Subject to Retention 1,549,215.57 73,261.16 5. Mobilization 6. Total Work Completed 1,549,215.57 7. Deductions -21,000.00 -21,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,528,215.57 52,261.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,261.16