Dept. of Trans. PROGRESS Serial No. Contract No. 13-151-09-08 02-4F4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 100% 02-SIS-5-44.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-22-12 ROAD AND HIGHWAY BUILDERS OF CA, INC. 2030 W. EL CAMINO AVE., #265 SACRAMENTO, CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,134.75 0.00 2.a. Extra Work 819,597.96 515,687.33 b. Adjustment Comp. -4,134.75 -4,134.75 3. Materials on Hand 4. Earned Subject to Retention 819,597.96 511,552.58 5. Mobilization 6. Total Work Completed 819,597.96 7. Deductions -10,000.00 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 809,597.96 503,552.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 503,552.58