Dept. of Trans. PROGRESS Serial No. Contract No. 21-327-14-23 02-4F5404 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 02-SIS-5-R15.3/R16.5 B1IM-005-9(179) Progress payment No. 017 Payment period ending: 11-20-21 J F SHEA CONSTRUCTION INC PO BOX 494519 REDDING CA 960494519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,573,856.55 497,558.00 2. a. Extra Work 91,667.49 28,770.98 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 7,665,524.04 526,328.98 5. Mobilization 450,000.00 0.00 6. Total Work Completed 8,115,524.04 7. Deductions -223,000.00 -214,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,892,524.04 312,328.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 312,328.98