Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-15-26 02-4F5904 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 9% Location: Federal Project: 02-TEH-5-R25.4/R25.4 NONE Progress payment No. 006 Payment period ending: 03-20-21 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,578,045.70 221,330.30 2. a. Extra Work 102,668.51 22,454.72 b. Adustment Comp. 25,691.50 0.00 3. Materials on Hand 257,698.00 17,342.00 4. Earned Subject to Retention 1,964,103.71 261,127.02 5. Mobilization 990,000.00 0.00 6. Total Work Completed 2,696,405.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,954,103.71 261,127.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,127.02