Dept. of Trans. PROGRESS Serial No. Contract No. 22-081-09-33 02-4F5904 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 63% Location: Federal Project: 02-TEH-5-R25.4/R25.4 NONE Progress payment No. 018 Payment period ending: 03-20-22 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,647,954.45 1,011,991.66 2. a. Extra Work 839,679.19 112,600.01 b. Adustment Comp. 149,066.78 0.00 3. Materials on Hand 792,129.00 138,683.00 4. Earned Subject to Retention 10,428,829.42 1,263,274.67 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 10,956,700.42 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,745,829.42 1,263,274.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,263,274.67