Dept. of Trans. PROGRESS Serial No. Contract No. 14-233-15-06 02-4F6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 58% 02-VAR Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-14 NACS INC C/O SHASTA CONSTRUCTORS INC 1710 DOUGLAS DRIVE N STE 109 GOLDEN VALLEY MN 55422 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 430,739.78 186,300.60 2.a. Extra Work 5,296.38 4,625.12 b. Adjustment Comp. 3. Materials on Hand 13,165.29 13,165.29 4. Earned Subject to Retention 449,201.45 204,091.01 5. Mobilization 144,400.00 30,400.00 6. Total Work Completed 580,436.16 7. Deductions -4,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 589,601.45 230,491.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,491.01