Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-13-00 02-4F6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 65% 02-VAR Federal Project: NONE Progress payment No. 07 Payment period ending: 11-18-14 NACS INC C/O SHASTA CONSTRUCTORS INC 1710 DOUGLAS DRIVE N STE 109 GOLDEN VALLEY MN 55422 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 929,380.70 48,174.52 2.a. Extra Work 53,178.40 33,884.35 b. Adjustment Comp. 3. Materials on Hand 138,403.60 132,116.94 4. Earned Subject to Retention 1,120,962.70 214,175.81 5. Mobilization 152,000.00 0.00 6. Total Work Completed 1,134,559.10 7. Deductions -3,000.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,269,962.70 215,175.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 215,175.81