Dept. of Trans. PROGRESS Serial No. Contract No. 14-296-09-16 02-4F7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 76% 02-VAR Federal Project: NONE Progress payment No. 04 Payment period ending: 10-20-14 Q & D CONSTRUCTION INC. 1050 S. 21ST SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 832,569.44 264,601.28 2.a. Extra Work 123,028.39 93,916.96 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 955,597.83 358,518.24 5. Mobilization 103,000.00 0.00 6. Total Work Completed 1,058,597.83 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,056,597.83 358,518.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 358,518.24