Dept. of Trans. PROGRESS Serial No. Contract No. 18-361-15-35 02-4F77U4 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 44% Location: Federal Project: 02-MOD-299-23.1/33.5 ACNH-P299(201) Progress payment No. 006 Payment period ending: 12-20-18 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,494,773.21 358,623.61 2. a. Extra Work 225,024.21 32,230.86 b. Adustment Comp. -138,250.26 -138,250.26 3. Materials on Hand 4. Earned Subject to Retention 8,581,547.16 252,604.21 5. Mobilization 1,588,796.50 0.00 6. Total Work Completed 10,170,343.66 7. Deductions -14,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,156,343.66 252,604.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 252,604.21