Dept. of Trans. PROGRESS Serial No. Contract No. 19-056-16-43 02-4F77U4 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 44% Location: Federal Project: 02-MOD-299-23.1/33.5 ACNH-P299(201) Progress payment No. 008 Payment period ending: 02-20-19 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,589,511.86 23,634.00 2. a. Extra Work 324,512.46 83,630.56 b. Adustment Comp. -138,250.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,775,774.06 107,264.56 5. Mobilization 1,588,796.50 0.00 6. Total Work Completed 10,364,570.56 7. Deductions -10,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,354,570.56 105,264.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,264.56