Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-14-45 02-4F8604 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 71% Location: Federal Project: 02-TRI-36-26.7/27.1 HSST-S036(108) Progress payment No. 011 Payment period ending: 02-20-20 STEELHEAD CONSTRUCTORS INC PO BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,995,779.61 0.00 2. a. Extra Work 584,356.48 0.00 b. Adustment Comp. 3. Materials on Hand 145,577.80 20,060.60 4. Earned Subject to Retention 3,725,713.89 20,060.60 5. Mobilization 817,000.00 0.00 6. Total Work Completed 4,397,136.09 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,541,713.89 19,060.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,060.60