Dept. of Trans. PROGRESS Serial No. Contract No. 21-146-12-34 02-4F8604 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 76% Location: Federal Project: 02-TRI-36-26.7/27.1 HSST-S036(108) Progress payment No. 022 Payment period ending: 05-20-21 STEELHEAD CONSTRUCTORS INC PO BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,221,175.24 700,041.80 2. a. Extra Work 866,384.88 0.00 b. Adustment Comp. 1,175,138.30 209,640.50 3. Materials on Hand 22,060.60 -125,517.00 4. Earned Subject to Retention 9,284,759.02 784,165.30 5. Mobilization 860,000.00 0.00 6. Total Work Completed 10,122,698.42 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,144,759.02 784,165.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 784,165.30